# Epic Progress Report

"Epic is 60% done" is the least useful sentence in delivery — 60% of what, and is the remaining 40% the easy part or the terrifying part? This breaks the epic into its child work by status, surfaces the pieces most likely to blow the date, and — instead of just reporting — offers a cut menu and an honest read on whether the deadline survives contact with reality.

## What This Skill Produces

- **The completion picture** — child items grouped by status (done / in progress / not started / blocked), with what % and *which* work remains
- **The riskiest remaining work** — the unfinished pieces most likely to slip (unknowns, dependencies, the hard 20%)
- **The cut menu** — what could be descoped or deferred, and the impact of each cut
- **The date call** — will it make the target as-is; if not, what has to give

## Required Inputs

Ask for these if not provided:
- **The epic & its children** — the stories/tasks under it and their statuses (a board export or list)
- **The target date & goal** — what "done" means for this epic and when it's needed
- **Dependencies & unknowns** — anything waiting on another team, or work that's still fuzzy
- **Who it's for** — a standup, a stakeholder, or a go/no-go — tunes depth and bluntness

## Framework: Progress You Can Act On

1. **Remaining work, not just percent.** Report what's *left* and how hard it is — the last 20% is often the risky 80%.
2. **Status by child, honestly.** Blocked and not-started are different from in-progress; don't average them into a comforting number.
3. **Name the riskiest pieces.** Dependencies, unknowns, and the one hard component are where dates die — call them out.
4. **Offer cuts, don't just warn.** A scope-cut menu with impact turns "we might slip" into a decision the team can make.
5. **Give a straight date call.** "On track," "at risk — here's why," or "won't make it without cuts." Vague green status is the enemy.

## Output Format

### Epic: [name] · target [date] · for [audience]

### Completion
| Status | Count | Which work |
|---|---|---|
| ✅ Done | | |
| 🔨 In progress | | |
| ⬜ Not started | | |
| ⛔ Blocked | | |

### Riskiest remaining
- [item] — why it's risky (unknown / dependency / complexity).

### Cut menu (to protect the date)
| Could cut/defer | Saves | Impact if cut |
|---|---|---|

### Date call
> **On track / At risk / Won't make it without cuts** — because [reason].

## Quality Checks
- [ ] Remaining work is described, not just a percentage
- [ ] Children are grouped by real status (blocked ≠ in-progress ≠ not-started)
- [ ] The riskiest unfinished pieces are named with why
- [ ] A concrete cut menu with impact is offered, not just a risk warning
- [ ] A straight date call is made — not a vague "green"
- [ ] No invented statuses — unknowns are marked unknown

## Anti-Patterns
- **A single % with no breakdown** — hides where the risk is.
- **Averaging blocked and not-started** into a reassuring number.
- **Warning of slip with no options** — leaves the reader stuck.
- **Watermelon status** (green outside, red inside) — a comfortable date call that isn't true.
- **Guessing a child's status** instead of flagging it unknown.

## Example Trigger Phrases
- "Give me an epic progress report for the checkout revamp."
- "Where are we really on this initiative, and can we cut to hit the date?"
- "Break down this epic's status by child work and flag the risky bits."
- "Is this epic going to make the deadline? What would we have to drop?"